92% adherence—should we punish production or planning?
Split the 800 units by reason code. Material and tooling are joint ownership; only pure capacity shortfall is operations alone.
Schedule Adherence: plain-English definition, formula, worked example, how to interpret the result, peer-based benchmark guidance, common mistakes, and management actions in the ZBI Business Control Library.
Schedule adherence compares what the shop floor actually produced against the quantity on the frozen weekly plan—same period, same units. It shows whether planning releases were executed, not whether customers received on time. IndustriServis d.o.o. in Rijeka planned 10,000 units and finished 9,200—adherence 92%, meaning 800 planned units never landed when the schedule said they would.
At 92% adherence, 800 planned units did not arrive when kitting and downstream assembly expected them—expedite freight replaces rhythm and internal milestones slip. Chronic adherence below plan teaches sales not to trust portal dates you publish. High adherence with rising WIP can still mean building the wrong sequence—pair with on-time delivery. When planners cut planned volume 10% mid-week without telling commercial, adherence jumps but service does not improve. Labour schedules and supplier ASNs assume the released plan is real; weak adherence breaks that promise to your own floor.
Schedule Adherence % = Actual Production per Schedule ÷ Planned Production × 100
Actual production per schedule — good units completed against the official plan in the period.
Planned production — released schedule quantity for the same horizon and unit.
Excel: =IFERROR(B2/B3*100,0)
IndustriServis d.o.o., a maintenance supplies manufacturer in Rijeka, closes Week 19: planned production 10,000 units on the CNC cell per the frozen weekly plan; actual good output against that plan 9,200 units. Schedule adherence = 9,200 ÷ 10,000 × 100 = 92%. Week 18 was 96%—the gap is 300 units lost to an unplanned tool breakage and 500 units deferred when inbound steel arrived two days late. Planning freezes Week 20 at 9,500 units until material coverage is confirmed.
Adherence measures execution against the plan you actually released.
Many discrete manufacturers target 92–98% adherence on frozen weekly plans; custom job shops run lower when engineering changes are daily. Benchmark against your own four-week rolling average and against the adherence assumed in MRP infinite-capacity flags—not a generic 100%. Peers with high mix accept 88–92% if on-time delivery still clears 95% on A-class orders—know which trade-off you chose.
Split the 800 units by reason code. Material and tooling are joint ownership; only pure capacity shortfall is operations alone.
Yes—track 'unplanned change' percent separately. Chronic pull-ins mean commercial and planning need a different freeze policy.
Check on-time delivery and correct SKU mix—you may hit volume on the wrong orders.
Define policy: e.g. frozen after Thursday 12:00 for the following week. Document exceptions.
Align adherence cut-off with inventory transaction rules or measure at shift complete with barcodes.
Schedule adherence compares actual output to the released plan. Freeze the baseline, classify misses honestly, and pair with on-time delivery so quantity and date both hold.
Reviewed by ZBI Business Control Library · Last updated 2026-06-15